ALL PROJECTS AS OF March 3, 2020

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141. (See More Info.)
Jefferson County Utility Relocation (Notice to proceed with construction has been issued) 80% Construction
04/20
Eden Ridge at S. Shades Crest Rd - Adds left turn lane to South Shades Crest Rd and realigns Shades Run Circle. ALDOT Construction 99% Project Closeout with ALDOT 04/20
Galleria Blvd Extension - County lead project that extends Galleria Blvd. by Chick-Fil-A to Old Montgomery Hwy.  For additional information on this project, contact Jefferson County Roads​ and Transportation at (205) 325-5141. Jefferson County ROW Acquisition 50% Utility Relocation 10/20
Hwy 150 Right Turn Lane @ Whisperwood Ln City of Hoover Bid Process 25% Construction 06/20
Valleydale Rd/Highway 261 Widening - Widens Valleydale Rd/Hwy 261 from Riverchase Pkwy to Bearden Rd. (collaborative effort with Shelby County)
ALDOT Design 70% ROW Acquisition Summer 2020
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​12 Pending​
85% Utility Relocation Summer 2020
Stadium Trace Pkwy at Brocks Gap Pkwy - Adds new turn lanes and extends existing turn lanes for each of the four intersection approaches. City of Hoover Construction
100% Closeout 03/20
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes drive to Hwy 150.                Jefferson County      Permitting Process 70% Construction TBD - Coordinating efforts with Jefferson County & CSX Railroad

SIDEWALKS, GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave.  (See more info.) ALDOT ROW Acquisition
​30 Total tracts
​1 Pending 
97% Utility Relocation 04/20
Cahaba/Riverchase Greenway - Constructs parking, trail head and new trail on city-owned property adjacent to Riverchase Elementary school and the Cahaba River. City of Hoover Construction 100% Project Closeout with ALDOT 04/20
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT Design & Planning  5% ROW Acquisition TBD
Bluff Park Sidewalks - Constructs sidewalks on multiple streets in Bluff Park. (See More Info.)
ALDOT Construction <5% Completion Fall of 2020
Municipal Ln & Municipal Dr Sidewalks
City of Hoover Bid Process 80% Construction
05/20
Alford Avenue Sidewalks, Phase 1 - Constructs sidewalk along Alford Avenue from Haden Street to Pine Lane and along Haden St from Alford Ave to Blue Ridge Blvd. (See More Info.)
City of Hoover Right-of-way Acquisition 50% Bid Process 05/20
Inverness Community Greenway - Constructs sidewalk and trail along Inverness Parkway from Valleydale Rd, through the City's Inverness Nature Park. (Awaiting environmental review) ALDOT Environmental Impact Updates
90% Bid Process Summer 2020

PARKS & FACILITIES

         
Bluff Park Pavilion - Replaces aging community center with a pavilion. City of Hoover Value Engineering      
Police Training Facility - Constructs new police training facility on Municipal Drive next to Fire Station 4. City of Hoover Construction 30% Completion Summer 2020
City Hall 3rd Floor Renovations - Renovate 3rd floor city hall administrative offices and Council Chambers. City of Hoover Construction 35% Completion 10/20
Star Lake Improvement - Upgrades Star Lake Park by creating one-way traffic around the lake, widening and replacing the existing sidewalk and improving parking. (See More Info.)
City of Hoover Value Engineering 75% Construction Summer 2020

GENERAL / MISC

.
         
US Hwy 31 Street Light Replacement, Phase 2 - Installs new street lighting along Hwy 31 from Patton Chapel Rd to I-65. ALDOT Design

95% Construction
Fall of 2020
Traffic Signal Modifications Upgrade, Hwy 31 at Deo Dara Dr. City of Hoover
Equipment Procurement
95% Completion
04/20
Traffic Signal Addition - Stadium Trace Pkwy @ Flemming Pkwy City of Hoover Equipment Procurement   75% Construction      07/20
Marywood Drainage Improvements City of Hoover Bid Process 50% Construction 04/20
Upgrade Inverness Pump Station Telemetry City of Hoover Bid Process 50% Construction TBD
Upgrade Riverchase Pump Station Telemetry City of Hoover Bid Process 50% Construction TBD
Upgrade Woodford Pump Station City of Hoover Bid Process 50% Construction TBD
Inverness WWTP Filter Rehab
​ Repairs Existing Filters
City of Hoover Procurement 30% Construction 02/20